15 Pa over the corridor, measured and signed in the OQ report. The inspector's question is why 15.

The URS only says "positive pressure", the calculation that set the airflow offset lives on someone's laptop, and the schematic shows a setpoint with no reference. Each figure may be right, but none of them can be traced. A passed test nobody can link back to a requirement is a frequent gap in qualification files.

A traceable chain looks like this:

  1. Requirement. The URS line, with a number: Grade B filling room at least 10 Pa above the Grade C corridor, with recovery after a door opening inside a stated time.
  2. Calculation. The airflow offset sized from door gaps and construction leakage, with the assumptions written down.
  3. Drawing. HVAC schematic and control narrative showing setpoint, alarm limits and alarm delay, each referencing the calculation.
  4. Test. The OQ protocol step that measures the differential and the door-open recovery, referencing the URS line it proves.

A traceability matrix links the four. When the answer to an inspector's question is a row number instead of a meeting, the audit gets shorter.

We start that matrix with the first design issue.

Industries

Related

More on this subject

PIC/S GMP and EU GMP: who issues the certificate

The PIC/S GMP Guide and EU GMP are almost identical, revised Annex 1 included. In the EU the GMP principles are set in law and certificates sit in EudraGMDP; PIC/S authorities adopt the guide nationally and PIC/S certifies nothing. One design serves both; the EU inspection route is planned separately.