PW and WFI: sampling points are drawn on the P&ID

  • Life Sciences
  • 1 min read

Annex 1 (2022) clause 6.13 asks for at least one representative sample every day of manufacturing water.

Where it is taken is decided on the P&ID.

The same clause wants the sampling program to cover all outlets and points of use, and to consider worst-case locations. That is easy to write into an SOP and hard to do on a loop where half the user points sit behind equipment or high in a ceiling void.

What belongs on the P&ID before the isometrics are issued:

  1. A sample valve at every point of use, reachable from the floor, placed so the sample comes out the way production draws water: through the same valve and, where production uses a hose or transfer line, through that too.
  2. Sample points after each point-of-use sub-cooler, where the water sits cooler than the loop.
  3. The end of the loop return, often the worst-case location in a distribution system.
  4. Enough flow and a drain at each point to flush before sampling without flooding a clean area.

A loop that needs a ladder for its daily sample tends to get sampled wherever is convenient.

Industries

Related

More on this subject

What ends the life of a HEPA filter

EU GMP Annex 1 (2022) asks for an integrity test of final filters at requalification and puts no age on the filter. A terminal HEPA is replaced when a leak cannot be repaired within site limits, when pressure drop reaches the manufacturer's final value, or after damage or wetting. On glass-fibre media, dust loading alone does not lower efficiency.

InsightRead

From Viet Nam to Europe: three registration pathways

A Vietnamese manufacturer can reach the EU market by acquiring a marketing authorisation and transferring the site, by new registration via technology transfer, or by in-house development. All three need an EU GMP site and quality system, an EU-based MAH, a Qualified Person and pharmacovigilance.

InsightRead

The CCS is where design decisions get defended

Under EU GMP Annex 1 (2022), the Contamination Control Strategy has to connect barriers, airflow, personnel and material flows, cleaning, utilities and monitoring. A useful test for any CCS: every line should point to a drawing, calculation or test, not to a procedure written after construction.

Read