Annex 1 (2022) clause 6.13 asks for at least one representative sample every day of manufacturing water.
Where it is taken is decided on the P&ID.
The same clause wants the sampling program to cover all outlets and points of use, and to consider worst-case locations. That is easy to write into an SOP and hard to do on a loop where half the user points sit behind equipment or high in a ceiling void.
What belongs on the P&ID before the isometrics are issued:
- A sample valve at every point of use, reachable from the floor, placed so the sample comes out the way production draws water: through the same valve and, where production uses a hose or transfer line, through that too.
- Sample points after each point-of-use sub-cooler, where the water sits cooler than the loop.
- The end of the loop return, often the worst-case location in a distribution system.
- Enough flow and a drain at each point to flush before sampling without flooding a clean area.
A loop that needs a ladder for its daily sample tends to get sampled wherever is convenient.