Qualifying a battery dry room: four tests

  • Renewable Energy
  • 1 min read

Signed off on one dew-point reading in the return duct, a battery dry room has proved very little.

The return duct sees mixed air. The product sees the air at the coating line and the stacking bench. Four tests say much more, with acceptance criteria agreed in the protocol before anyone runs them.

  1. Dew-point mapping. Portable trace-moisture probes at working height across the room, at rest and in operation, read alongside the fixed sensors. The map also shows where those sensors should have gone.
  2. Recovery after a door event. Hold the airlock door open for a set time, close it, and record how long the room takes to get back inside its dew-point limit. Production will open that door many times a shift.
  3. Envelope leak test. Pressurise the room and measure the make-up air it takes to hold a test pressure, or smoke-test the joints and penetrations. A leak found now costs sealant.
  4. Calibration first. Every sensor used in the tests needs a current, traceable calibration checked at the dry end of its range. A sensor a few kelvin off can pass a room that fails.

The limits come from what the cell chemistry tolerates, and the process team has to write them down before the test.

We design Li-ion dry rooms to −60 °C dew point and below; these tests show whether the room holds its limit in production.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead