Skip to content

Manufacturing & Distribution

Five punch items AHU factory tests keep catching

  • Manufacturing & Distribution
  • 1 min read

A 0–10 V humidity transmitter on an AHU whose IO list says 4–20 mA will pass a visual FAT and fail the first loop check on site.

That mismatch is one of five defects that turn up at AHU factory acceptance tests again and again. Each is easier to fix before the unit leaves the factory.

  1. Transmitters wired for the wrong signal type, two-wire loop-powered sensors landed on an input card that gives no loop power, and humidity sensors delivered with no calibration certificate.
  2. Valves, sensors and dampers with no tag, or a tag that differs from the P&ID and IO list. IQ slows down.
  3. Door and panel gaskets that do not close at the corners and hinges. A light along the seam with the fan running finds them. A gap next to the filter frame later shows up as bypass.
  4. A drain pan that still holds water after a test fill, or a trap height that does not suit the fan pressure on that section. Water left under a cooling coil grows biofilm.
  5. Wiring diagrams still as first drawn, and material certificates, weld or passivation records missing where they apply. Ask to see the file at the FAT.

Take the approved specification and the IO list to the test and check each item against those two documents.

Every Humiley unit is FAT-tested and witnessed, and the equipment file is compiled during production so IQ starts from a complete record.

Related

More on this subject