Cleanroom OQ: the order the tests run in

  • News
  • 1 min read

Count particles before the filter leak test and you may have to throw the result away.

If the scan then finds a leak, the filter is repaired or replaced, and the classification has to be run again on the room as it now stands. Cleanroom OQ tests depend on each other, so their order is part of the protocol.

  1. Measure airflow volume and velocity first, and finish the balancing. Everything after this assumes the design air quantity.
  2. Set and record the pressure differences between rooms with all doors closed. Any later rebalancing moves them.
  3. Scan the installed filters for leaks at the airflow now fixed. Repairs happen here, before anything counts particles.
  4. Run the airflow visualization. It shows whether the air goes where the design says, and of all the tests it is the likeliest to send you back to step 1.
  5. Classify the room, then run the recovery test. They come last because the aerosol from the leak test and the smoke study has to clear first.

ISO 14644-3 gives the methods for the supporting tests in steps 1 to 5; the classification itself is to ISO 14644-1. ISO 14644-3 does not set the order: it says its tests are not presented in chronological order, so the sequence belongs in the site's OQ protocol.

Smoke studies are often filmed late, because the camera and QA are booked for one day, and that puts step 4 after step 5. It works only if nobody expects the video to move a diffuser.

Related

More on this subject

Energy savings and the requalification bill

Energy measures that change validated cleanroom conditions go through Annex 15 change control. Classification alone can mean 10 sample locations for a 50 m² room, at rest and in operation, before recovery tests and a CCS update. Price that next to the kWh, or design reduced modes in and qualify them once.

InsightRead

ISO Class 1 vs ISO 5: counting at 0.1 µm

ISO Class 1 allows 10 particles of 0.1 µm and larger per cubic metre; ISO 5 allows 100,000 at that size. At that level the installed leak scan must prove frames and grid, not just the U15 filter, single-digit counts need large sample volumes, and airborne molecular contamination needs its own sampling plan.

InsightRead

Both states are required; only the stage is a choice

A 50 m² Grade B room needs 10 classification locations under ISO 14644-1:2015, and EU GMP Annex 1 requires them at rest against ISO 5 and in operation against ISO 7, with the smoke study in both states. Whether each run sits in OQ or PQ is for the URS and risk assessment to justify.

InsightRead