On a compressed air specification, 1:2:1 is three separate limits in a fixed order.
The notation is from ISO 8573-1:2010: the first digit is particles, the second water, the third oil.
Particle classes 1 to 5 are counts in three size bands. Class 1 allows, in each cubic metre, no more than 20,000 particles of 0.1 to 0.5 µm, 400 of 0.5 to 1 µm and 10 of 1 to 5 µm.
Water classes 1 to 6 are pressure dew points, and class 2 is −40 °C or lower. The value is stated at line pressure: −40 °C at 7 bar gauge is about −57 °C once the air is let down to atmosphere, so a hygrometer on an open sample line does not read the class value. Oil is total oil, liquid, aerosol and vapour together, and class 1 is 0.01 mg/m³ or less.
Write the designation in full, year included: ISO 8573-1:2010 [1:2:1].
The class does not say where it applies, so name the point of use; a dryer outlet proves nothing about the far end of the ring main. Class 0, often read as zero, is a limit specified by the equipment user or supplier, tighter than class 1.
What class is on your point-of-use drawing, and who measured it there?