Hygienic and commercial AHUs, side by side

  • Manufacturing & Distribution
  • 1 min read

At FAT, a bucket of water poured into a hygienic AHU drain pan should reach the outlet, every drop of it.

Water left under a coil over a weekend is where microbial growth in an AHU usually starts. A hygienic unit gives it nowhere to sit, starting with the drain pan: sloped to the outlet, draining completely, no corners. The rest sits in details a quotation rarely lists.

Commercial casings often leave insulation edges, rivet heads and ledges in the airstream. A hygienic unit keeps inner surfaces smooth, closed and wipeable, and gives every section that needs cleaning a door big enough to reach inside. A panel held on by a ring of screws rarely gets opened.

Fan, coil and humidifier parts should come out for cleaning outside the casing. Filter frames have to seal, since a frame leaking around its edge makes the filter class irrelevant; EN 1886 rates filter bypass leakage, and F9 is the class to ask for when fine filters are fitted.

The paperwork belongs to the unit as well: material certificates, weld and passivation records, the FAT report and O&M manuals, compiled while it is built.

Write each of these into the specification as something that can be seen or tested at FAT, the drain pan emptying included.

AeroSano, Humiley's hygienic air handling brand, supplies units built by qualified partners under Humiley engineering control, each FAT-tested and witnessed.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

One differential gauge per filter stage

A single differential gauge across several AHU filter stages cannot say which stage loaded, so teams change everything or guess. A gauge per stage, marked with the commissioning reading and change limit and kept on the calibration list, allows each stage to be changed on condition. BMS transmitters add a trend.

InsightRead

Clean AHU cooling coils from the leaving face with low-pressure water or steam and an approved, fully rinsed detergent, after checking the drain. Take the frequency from the coil's pressure drop trend against a commissioning baseline, and record the method, detergent batch, before and after readings and photos of both faces.

InsightRead

Manufacturing & Distribution

Plug fan or belt drive in a GMP supply AHU

A V-belt sheds rubber dust into the airstream for its whole life, and in a GMP supply AHU that dust loads the final filters. Belt drives also lose a few per cent of shaft power and need regular tensioning. Direct-drive plug fans avoid all three, though a large belt-driven housed fan can still win at high pressure.

InsightRead