On an equipment-only AHU order, send your own engineer to watch the casing leakage test at FAT and read the figure off the instrument.
Buying units directly while a contractor builds the plant is normal. The document trail between the two belongs to nobody unless the purchase order names it, and IQ is where that gap shows.
Start with the casing. EN 1886 grades casing air leakage in classes such as L1 and L2, and rates filter bypass leakage, with F9 the class to ask for when fine filters are fitted. Write the classes you need into the order and state that they will be demonstrated on the built unit at FAT, because the class on a datasheet belongs to the model range and the unit you qualify has its own panel joints and door seals.
The same visit covers airflow, pressure, controls and alarms against the approved specification, with deviations written down before shipping. The selection should trace to your airflow schedule line by line.
Then ask for the file as it is built: material certificates, weld and passivation records, the FAT report, O&M manuals and the spares list. If it arrives with the unit, IQ starts from a complete record.
Humiley supplies equipment this way: built by qualified manufacturing partners under Humiley engineering control, each unit FAT-tested and witnessed, with or without our other divisions.