Equipment-only AHU order: what to write into the PO

  • Manufacturing & Distribution
  • 1 min read

On an equipment-only AHU order, send your own engineer to watch the casing leakage test at FAT and read the figure off the instrument.

Buying units directly while a contractor builds the plant is normal. The document trail between the two belongs to nobody unless the purchase order names it, and IQ is where that gap shows.

Start with the casing. EN 1886 grades casing air leakage in classes such as L1 and L2, and rates filter bypass leakage, with F9 the class to ask for when fine filters are fitted. Write the classes you need into the order and state that they will be demonstrated on the built unit at FAT, because the class on a datasheet belongs to the model range and the unit you qualify has its own panel joints and door seals.

The same visit covers airflow, pressure, controls and alarms against the approved specification, with deviations written down before shipping. The selection should trace to your airflow schedule line by line.

Then ask for the file as it is built: material certificates, weld and passivation records, the FAT report, O&M manuals and the spares list. If it arrives with the unit, IQ starts from a complete record.

Humiley supplies equipment this way: built by qualified manufacturing partners under Humiley engineering control, each unit FAT-tested and witnessed, with or without our other divisions.

How our Manufacturing & Distribution division works

Related

More on this subject

Five things a package needs before IQ

IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.

InsightRead

EN 1886 class L2 allows an AHU casing 0.44 l/s per m² of leakage at −400 Pa. On a witnessed FAT, casing leakage, fan airflow at design static pressure, filter bypass and the control panel are checked against the approved specification, and both engineers sign the sheet that goes into the equipment file.

InsightRead

An ISO 9001 certificate shows that a supplier's quality management system was audited within a stated scope. It does not show that the equipment or service you bought meets your requirement. Supplier qualification assesses what you buy, against your URS, to a depth set by risk: questionnaire, audit or factory hold points.