Panel labels that match the drawing

  • Manufacturing & Distribution
  • 1 min read

Terminal X12:7 is a spare on the drawing in the door pocket, and it is where the tripped AHU fan circuit lands.

From that moment fault-finding stops and guessing starts. Is the drawing old, or was the panel rewired on site? Either way the AHU stays down longer, and in a GMP area that means a longer excursion to investigate afterwards.

A control panel can be checked for this before it leaves the factory, and it is a cheap check.

Pick ten wires at random and trace each from the drawing to both ends. The ferrule at each end should carry the number the drawing gives it.

Read the device tags. The breaker, contactor or relay labelled Q14 should be the Q14 on the drawing and the bill of materials, with the rating the drawing states.

Open the door pocket. The drawing inside should carry the same revision as the one in the equipment file, and that revision should match what is wired.

Site changes are where panels and drawings drift apart. A marked-up drawing returned after commissioning keeps them together.