The door stands open for forty seconds; when it shuts, the room shoots to 32 Pa against a 15 Pa setpoint.
The first suspects are usually airflow: a damper too large, a leaky door. The trend log often points somewhere else. During those forty seconds the controller output runs to 0% or 100% and stays there.
With the door open the room cannot hold pressure, whatever the damper does. The PI loop sees a steady error and its integral term keeps adding it up. The damper reaches its end stop early, and the sum inside the controller carries on growing. That is integral windup.
When the door closes, the pressure recovers in a second or two, but the controller is still holding that inflated sum. The error has to sit on the other side of the setpoint long enough to work the sum back down before the damper moves at all. The room overshoots while it waits.
The cure sits in the controller. Anti-windup stops the integral once the output is at its limit. A door contact can hold the output at its last value while the door is open. Most BMS controllers offer at least one of these, and they are not always enabled.
Does your BMS trend the controller output next to the room pressure?