The isolator is locked off, and the fan wheel is still turning in the draught from the unit next door.
Two AHUs on a common duct do that. Air from the running unit leaks back through the stopped one and windmills its fan. A sleeve caught in the wheel does not care where the torque comes from, and a permanent-magnet EC motor that is being turned generates voltage at its terminals.
An AHU has more energy sources than its electrical supply, which is why the sequence in OSHA 29 CFR 1910.147 starts with knowing them. Local regulations apply on your site; check their steps against this order.
- Identify every source: fan and heater supplies, the control circuit, steam or hot water, chilled water under pressure, UV lamps, and moving air from connected systems.
- Shut down through the normal stop, then isolate each source: isolators open, valves closed, the duct damper shut and secured.
- Lock and tag. Each person working on the unit fits a personal lock and keeps the key.
- Release what is stored. Wait for the fan to run down and chock the wheel. Wait the discharge time marked on the drive. Vent and drain any coil that will be opened.
- Try to start it. Press the local start, confirm nothing happens, and test for voltage where you will work. Then open the door.
Stopping the unit from the BMS is not isolation. A fan stopped from the graphic restarts on the next schedule or the next operator click.