Low delta-T: 5 K on the drawing, 3 K in the plant

  • News
  • 1 min read

A chilled water plant designed for a 5 K temperature difference and running at 3 K needs about 67% more water for the same cooling.

Cooling delivered is flow times temperature difference. Hold the load and let ΔT fall from 5 to 3 K, and flow has to rise by 5/3, about 1.67 times. The pumps run harder, and the chillers stage on early because each machine reaches its design flow before it reaches its design load. The plant looks short of capacity when it is short of ΔT.

The causes usually sit at the coils, not in the plant room:

  1. Three-way valves at the coils bypass supply water straight into the return and dilute it.
  2. Fouled or undersized coils cannot take enough heat out of each litre, so the valve opens further.
  3. Off-coil setpoints lower than the rooms need drive valves wide open and send cold water back.
  4. Decoupler or bypass lines flow the wrong way when the secondary pumps overrun.

Adding a chiller treats the symptom. The fix is two-way or pressure-independent valves at the coils, clean coils, setpoints checked against the room requirement, and ΔT trended on the BMS so the drift shows up as a number instead of a complaint.

Our maintenance service includes condition monitoring and IIoT trending, and on a chilled water system ΔT is one of the first signals worth trending.

What ΔT does your chilled water plant actually run at on a wet-season afternoon?

Related

More on this subject

Remote monitoring for a GMP maintenance contract

A maintenance contractor's remote view should be read-only, with setpoints changed only under the site's change control. Its alerts watch the plant behind the room, such as fan speed, filter pressure drop and chilled water temperature, and the escalation path to site is written before the contract starts.

InsightRead

Read Annex 1 clause by clause before the inspection date

A Grade B room never retested for recovery after a ductwork change is an easy inspection finding, and six months earlier it is ordinary planned work. A written review reads Annex 1 clause by clause and gives each gap one row: clause, current state, risk, fix and rough size, finished before an inspection date is set.

InsightRead