One clock for the BMS, the EMS and the particle counters

  • News
  • 1 min read

Particle spike at 14:03, door alarm at 14:05, pressure drop at 13:58, on three clocks. Nobody can say which came first.

That is the normal state of a plant where the BMS, the EMS and the particle counting system came from different vendors, each keeping its own time. Internal clocks drift, and after a year the gap can be minutes. In an excursion investigation those minutes decide whether the door caused the spike.

ALCOA+ asks for contemporaneous records. A record stamped five minutes late sits next to the wrong cause.

What we write into the specification:

  1. Every server, controller, PLC and counter syncs to one NTP source with a secondary, and loss of sync raises an alarm.
  2. Data are stored in UTC, local time is a display setting, and the audit trail records the offset used.
  3. OQ reads every system's clock against the reference at the same moment and accepts within a stated tolerance. We would write ±2 seconds for NTP-synced systems, which a working NTP client holds easily. Then pull the sync source and confirm the alarm.
  4. Periodic review repeats the comparison, because a replaced controller can come back running on factory time.

UTC storage earns its place when one system is hosted abroad. Viet Nam is UTC+7 all year, while most US time zones move an hour twice a year, so mixed local timestamps can put events an hour out of order for part of the year.

Related

More on this subject

GAMP 5 Second Edition puts critical thinking first

GAMP 5 Second Edition (2022) scales validation effort to risk to patient safety, product quality and data integrity, and adds agile and cloud guidance. On a GMP BMS, test alarms, audit trail and data transfer deeply. A quick check: count low-risk functions that still carry full test scripts.

InsightRead

Data Integrity

You can have a flawless Grade A cleanroom and the most advanced equipment—but if your operational data (temperature, humidity, differential pressure, batch mixing parameters, etc.) does not comply with ALCOA+ principles (Accurate,…

InsightRead