Signed mechanically complete on Friday, construction dust in the new HEPA filters by Monday: one certificate let the fans start.
Nothing on that certificate needs to be false for this to happen. It records that the system is installed to the latest drawings, pipework pressure tested, ductwork leakage tested, cables insulation-tested and terminated, labels fitted, red-line markups handed over, and open punch items sorted into those that block the next step and those that can wait. The installing contractor signs, the owner's construction lead countersigns, and care of the system usually passes to the owner. Every item on it is static.
Starting a fan needs a different list: pipes flushed and cleaned, rooms and ducts clean enough to put air through new filters, instruments calibrated, motor rotation checked, safety interlocks live, commissioning procedures approved. None of it appears on a mechanical completion checklist.
That list is the ready-for-commissioning certificate. The commissioning lead signs it, because that person is accepting the system for testing. Keeping it as a separate signature is what makes somebody walk the rooms for cleanliness before the first start.
Our project teams take systems through FAT, SAT and commissioning into qualification, turned over package by package.
What does your ready-for-commissioning checklist hold that the completion one does not?