Clean the new AHU before its first fan run

  • Manufacturing & Distribution
  • 1 min read

The first time a new AHU runs on a building site, it breathes whatever the site is doing that day: cutting, grinding, sanding plasterboard.

Start it early to dry out the building or cool a site office, and the dust goes straight onto the coil fins, the drain pan and, if they are already fitted, the final HEPA filters. The filters are the expensive part. The coil is the hidden part: dust that bakes onto wet fins does not come off with a vacuum, and it shows up months later as pressure drop and lost capacity.

A sequence that works:

  1. Clean the casing interior and drain pan after installation, before power-on, and record it.
  2. Seal duct openings until the rooms are clean enough to connect.
  3. If the fan must run during construction, fit temporary pre-filters on every intake and treat them as consumables.
  4. Fit the final filters only after the rooms have had their final clean, then run the installed leak test.
  5. Put the clean-before-start record in the turnover package, where IQ will look for it.

None of this is exotic. It gets skipped because the unit is ready before the building is, and somebody needs cold air. Qualification cannot start from an open punch list, and a dirty coil is a punch item nobody wrote down.

Who owns the first start-up on your projects: the contractor, the vendor or the commissioning team?

Related

More on this subject

Five things a package needs before IQ

IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.