A depyrogenation tunnel crosses the pressure cascade

  • Life Sciences
  • 1 min read

A depyrogenation tunnel is one of the few openings in a fill-finish cascade that stay open all shift, and it runs hot.

Its infeed sits in the washing room, often Grade D or C. Its outfeed delivers glass under Grade A air into a Grade B filling room. At a typical 10–15 Pa per grade, the two ends are one step apart from a Grade C wash room, two (20–30 Pa) from Grade D.

The tunnel has airflow of its own: HEPA-filtered air in the hot and cooling zones, and its own exhaust. The vendor balances those at FAT so that air inside moves from the cooling zone toward the infeed. Installed between two rooms, the room differential adds to that balance or works against it. Too much push from the filling side changes the flow through the hot zone, a condition the FAT heat-penetration runs never saw. Too little, and wash-room air has a route toward the outfeed.

Heat is the second interface. The hot-zone casing, the cooling-zone exhaust and the warm glass all land in the filling room's cooling load, beside the Grade A zone. The vendor has to give that figure zone by zone, in time to size the AHU.

The order matters. Tunnel balance and heat release go into the design basis first, then room pressures are set, then the rooms are balanced with the tunnel at temperature.

Humiley turns systems over package by package, so qualification starts from a balanced, verified installation.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Industries

Related

More on this subject

AHU casing deflection: D1 or D2

EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead