A maintenance planner who first sees the model at the 90% review can only ask for changes that now cost a redesign.
A common cadence on GMP projects is three model reviews, at about 30, 60 and 90% of detail design. The percentages matter less than two things fixed before the first: who attends, and what each review closes.
- At 30% the model shows rooms, grades, the pressure cascade, people and material routes, and where the plant rooms sit. QA and production belong in this one, because a gowning sequence or a waste route is still cheap to move. It closes the room data sheets and flow diagrams.
- The 60% model has ducts, main pipework, cable trays and equipment at their real size, with access and withdrawal zones. Maintenance walks it: filter changes, coil pulls, valve access, how a fan motor leaves the plant room.
- By 90% the questions are small and many. Penetrations through the cleanroom envelope, ceiling grid, supports, sensor and sampling points. QA checks the sampling points against the room data sheets, and validation looks for test ports where the protocols will need them. What remains open goes into a log with an owner and a date.
A comment that arrives after its review has closed goes through change control, with a drawing revision attached.
Our design is BIM-coordinated, and our project management consultancy runs stage gates from concept to PQ.