What 100 Pa of fan pressure costs over a plant's life

  • News
  • 1 min read

A 10,000 m³/h supply fan working against 1,500 Pa uses about 61 MWh a year. Most of that pressure was chosen on a drawing.

Fan power is airflow times pressure divided by efficiency. 10,000 m³/h is 2.78 m³/s. At 1,500 Pa total and an overall fan, motor and drive efficiency of 0.6, that is 2.78 × 1,500 ÷ 0.6 ≈ 6.9 kW. A cleanroom AHU runs 8,760 hours a year, so 6.9 kW becomes about 61 MWh.

Now take 100 Pa out. The same sum gives about 0.46 kW, or roughly 4 MWh a year, for every year the plant runs, on one AHU.

Where the 100 Pa usually hides:

  1. Duct velocities chosen to fit a shaft that was drawn too small.
  2. Filter banks with too little face area, so the dirty-filter pressure is high.
  3. A coil with a row more than the dehumidification load needs.
  4. Tight bends and transitions at the AHU connections, where the ducts ran out of space.
  5. Silencers added late because the fan was noisy at a pressure it did not need.

None of these is a big decision. Each is made by someone sizing one component, usually without seeing the fan power. By the time the fan is selected, the pressure is a given.

We set a pressure budget per AHU in the design basis and check duct and component selections against it. It is one of the places where our energy modeling, which targets a 30% reduction in HVAC energy, finds real kilowatts.

If you want the sum run on your own units, write to contact@humiley.com or call +84 28 7777 6668 (Viet Nam office).

Related

More on this subject

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.

InsightRead

Energy savings and the requalification bill

Energy measures that change validated cleanroom conditions go through Annex 15 change control. Classification alone can mean 10 sample locations for a 50 m² room, at rest and in operation, before recovery tests and a CCS update. Price that next to the kWh, or design reduced modes in and qualify them once.

InsightRead