A new AHU added to a running suite moves the pressure cascade.
Its requalification therefore reaches the differential at every door it serves, as well as its own filters. That is event-driven requalification, and the change control impact assessment sets its scope. Smaller changes reach less far. A replaced terminal HEPA needs a leak test of that filter and probably an airflow check for the room, while a moved wall can pull in classification, recovery time and a new smoke study.
The calendar trigger runs alongside it. Annex 15 expects facilities, utilities and systems to be evaluated at an appropriate frequency to confirm they remain in a state of control. For cleanrooms and clean air equipment, Annex 1 (2022) caps the interval at 6 months for Grade A and B and 12 months for Grade C and D, with the test set fixed in advance.
The two meet in one place. An event requalification resets the periodic clock only if its scope covered the periodic test set. If it tested one filter, the room keeps its next periodic date. Your procedure should state which reading it uses.
Periodic requalification and calibration are part of our Maintenance Service.
Industries