About 48 g of water walks into a battery dry room every time its door opens straight onto the plant room.
The sum is short. A door swing and the person going through it exchange something like 2 m³ of air. Plant-room air in southern Viet Nam holds around 20 g of water per kilogram, and 2 m³ is about 2.4 kg of air. That is 48 g in a few seconds, about as much as one operator gives off in a quarter to half an hour, depending on how hard they are working.
Then the room has to absorb it. Take a room held at −40 °C dew point, about 0.08 g/kg, supplied with air dried to −50 °C, about 0.02 g/kg. Each kilogram of supply can pick up only 0.055 g. Removing 48 g takes roughly 880 kg of supply air, around 730 m³. At 6,000 m³/h that is seven minutes of the full supply doing nothing else, and the dew point near the door spikes while it happens.
Three design choices follow. An airlock with its own dry supply, so the door opens onto air that is already dry. An interlock that stops both airlock doors opening together. And door-open time counted in the moisture load, because a trolley held in the doorway for 30 seconds swaps far more than 2 m³.
Humiley engineers dry rooms to −60 °C dew point and below, and the door schedule goes into the load calculation next to the envelope.
How many door openings an hour does your dry-room load assume?