P-F interval: what decides how often to inspect

  • Maintenance Service
  • 1 min read

Monthly vibration routes cannot catch a bearing fault that goes from first trace to seizure in two weeks.

P is the point where a failure first becomes detectable: a new peak in the vibration spectrum, a rise in bearing temperature, metal in the grease. F is functional failure, the moment the fan no longer delivers its air. The time between the two is the P-F interval, and it sets how often you need to look.

SAE JA1011, which sets the criteria for reliability-centred maintenance, requires the task interval to be shorter than the shortest likely P-F interval, with enough time left after detection to act. A common starting point is half the interval.

So the calendar has no say: "monthly" suits one failure mode and is useless for another on the same machine. P also moves with the method. Vibration analysis usually sees a bearing defect before a hand on the housing feels heat.

Where the interval is shorter than any route you can afford, the choice is a fixed sensor with trending (the condition monitoring and IIoT trending part of our maintenance service), or accepting the failure and holding the spare.

For which failure mode on your AHUs do you know the P-F interval?