An AHU runs for six years without a fault, then loses a fan bearing eight days after its annual strip-down.
The belts were re-tensioned during the service, a little too tight. Nothing was wrong with the bearing before the unit was opened.
Planned maintenance rests on one assumption: parts wear with age, so replacing or overhauling them on time prevents failure. For a belt or a lamp that holds. Reliability studies of airline maintenance in the 1970s found that many failure modes do not behave that way. Their chance of failing is no higher late in life than early, and a fixed overhaul cannot prevent them.
It can add new ones. Every intrusive task carries a chance of leaving something behind: a gasket pinched in an access door, a sensor not plugged back in, a drain trap left dry, a filter not seated in its frame. Those failures show up in the first days after the work.
Sorting the task list deals with both. Wear-out items stay on the calendar. For the rest, watch condition through vibration, bearing temperature, motor current and filter pressure drop, and open the machine when a reading gives a reason. After any intrusive job, compare the first run with the baseline before handing the unit back. Our maintenance service covers criticality-based planned maintenance, condition monitoring and IIoT trending.
Which task on your PM plan has never found anything?