Two vendors can both meet a tender's cooling kW for a fresh-air coil and still send air of different dryness to the same rooms.
Total kW hides the split between sensible and latent load. Chilled water temperature, the number of rows and the fin spacing decide how much of that capacity takes water out of the air, and on a fresh-air coil in Viet Nam the water is what the rooms care about. A datasheet line asking only for airflow and kW leaves the leaving dew point to each vendor's selection software, and the bids come back impossible to compare.
The coil should go to tender on the conditions the design already worked out. That gives the line seven fields: airflow; entering dry bulb and wet bulb at the wet-season peak dew point case; required leaving dry bulb; required leaving dew point; chilled water supply and return temperatures; maximum face velocity; and maximum air-side pressure drop. The last two keep a bidder from meeting the others with a small, fast coil that throws water into the filters and costs fan power for the life of the unit.
When the printouts arrive, check the entering condition first. A selection run at a different design point goes back for reselection before anyone looks at its price.
Design into procurement is one of the four handovers we manage, and there the coil line is filled from the project's own load calculation.
Which of those seven fields is missing from your current AHU tender template?