A casing panel that bows under fan pressure works its joints loose, and the leakage class you paid for goes with it.
EN 1886 rates AHU casing strength by relative deflection under a test pressure. D1 allows up to 4 mm per metre of span, D2 up to 10 mm/m, D3 more than that. Air leakage (L1, L2) and filter bypass are tested separately, but they are not independent of stiffness. A panel that flexes loads its gaskets and fixings every time the fan starts and stops.
For a comfort unit at modest static pressure, D2 is usually enough. A GMP supply unit tends to be different. It carries bag filters, sometimes an in-unit HEPA stage, a coil deep enough for a low dew point, and ductwork feeding terminal HEPA filters. Fan pressure is higher, and it climbs further as the filters load. The sections either side of the fan see the largest difference to the plant room.
On the suction side, a leak between the filters and the fan pulls plant-room air in behind the filters. On the discharge side, conditioned air escapes and the airflow the rooms receive falls short of what the fan moves.
Two questions for the supplier. Which class was the casing tested to, and on what model box? And is the unit's design pressure, dirty filters included, inside the test conditions?
Our AHUs are engineered from the project's airflow schedule and load calculation, and every unit is FAT-tested and witnessed.
Industries