Two envelopes for a cleanroom HVAC tender

  • Manufacturing & Distribution
  • 1 min read

Technical scores written after the prices are known have a way of drifting toward the cheapest bid.

That is why a cleanroom HVAC package is better evaluated in two envelopes. The technical envelope is opened, scored and signed off first. Only then does anyone see a price.

The scoring sheet should exist before the bids arrive, and it should go out with the tender so bidders know what counts. It has two parts.

The first part is mandatory items, pass or fail: AHU casing classes to EN 1886 as specified, filter classes to EN 1822 and ISO 16890, a witnessed FAT against the approved datasheet, and an equipment file with material certificates. A bid that fails one of these is out, whatever it costs.

The second part weights everything else. One workable split puts 40% on technical depth (fan selection and efficiency, coil selection at the design dew point, controls) and 20% each on documentation and qualification support, on the delivery and installation plan, and on service and spares in the region. Each criterion gets a written scale, so two evaluators scoring the same bid land close together.

Read the bidder's deviation list line by line and score it. A "complies with minor deviations" often hides the dew point.

Humiley's project management work covers the design-to-procurement handover, which is where this sheet gets written against the design basis.

Related

More on this subject

A retention that pays for the turnover file

Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.

InsightRead

Value engineering after tender: savings that return at OQ

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.

InsightRead

Engineering Solution & Consultancy

When the design exists: what EPCM takes on

Owners holding a finished design need someone to run the build against it, while the design stays with the designer of record. Design gaps are best listed at the first stage gate in five columns: the drawing, what is missing, the activity blocked, who closes it, and a date taken from the blocked activity's schedule.

InsightRead