100 Pa of extra filter resistance on a 10,000 m³/h supply costs about 460 W of fan power, around 4,000 kWh a year of continuous running.
That is the figure to put against the price of a filter set. 10,000 m³/h is 2.78 m³/s; multiply by 100 Pa, divide by a fan system efficiency of 0.6, and you get roughly 460 W. A GMP supply AHU runs all year, and so does that penalty.
The change point worth finding is the one with the lowest total cost per month, filters and energy counted together. It takes four inputs:
- Airflow and running hours per year.
- Electricity tariff and fan system efficiency.
- Price of the filter set, with labour and disposal.
- The pressure drop trend of that stage since the last change.
From the trend, add up the extra energy cost month by month. Change when the extra energy cost of the latest month rises above the average monthly cost since fitting, filter set included. Before that point, carrying on is cheaper; after it, a new set is.
Two limits sit above the sum: the filter manufacturer's maximum final pressure drop, and the airflow the fan can still hold at that resistance. The economic point only counts if it falls below both.
Our maintenance service runs criticality-based plans with condition monitoring, so the pressure drop trend is already in the record.
Who set the change limit on your AHU filter gauges, and from what?