About 3.4 kW of cooling disappears when 5% of a 10,000 m³/h supply at 12 °C leaks out of its duct into a 32 °C ceiling void.
The sum: 500 m³/h is about 600 kg/h of air, warmed by 20 K, at about 1.02 kJ/kg·K (moist air). That is 3.4 kW of sensible cooling, before counting the water the coil already took out of that air. The chiller produced it and the void received it.
Those 500 m³/h were also in the airflow schedule, so the room is short of supply, its pressure differential slips, and the balancing contractor opens dampers further to make up. The fan then works harder to feed the leak.
Leakage into an unconditioned space deserves more attention than leakage inside the room a duct serves, where the air still arrives. In the specification that means three things:
- An airtightness class for the ductwork, named against the European standard the fabricator works to, with a tighter class for runs through hot voids.
- A pressure test of those runs before the insulation goes on, while leaks can still be found and sealed.
- Joints, access doors and damper spindles included in the tested length, since that is where leaks usually sit.
Humiley's designs are BIM-coordinated, which shows early which duct runs cross unconditioned voids.
What leakage class did your last ductwork specification ask for?