Humidity control usually fails on a mild, saturated night with half the room empty, a load case many calculations never run.
Peak sensible and peak dew point are the design days everyone checks. Now take 25 °C outside, near saturation after rain, on a night shift with a third of the usual people and half the equipment off. The sensible load inside is small. The latent load from the fresh air hardly changes, because the fresh-air volume is set by the pressure cascade, not by the people.
If the coil valve is controlled on room or supply temperature, it throttles as soon as the room is cool enough. The coil warms up, its leaving dew point rises, and RH climbs while the temperature reads perfectly. It is the classic part-load failure in humid climates.
Run the case in the load calculation:
- Use the dehumidification design condition, dew point with its mean coincident dry bulb, as well as the cooling design day.
- Run it again at the lowest realistic occupancy and equipment load.
- Control the coil on leaving-air dew point and let reheat look after temperature.
- Size reheat for full latent load with close to zero sensible load, and check the chiller turns down that far.
Where the numbers still do not close, drying the fresh air in its own stage is usually cleaner than oversizing reheat.