Clean-utility slopes are lost in the ceiling void long before anyone welds a pipe.
A purified water or pure steam line has to drain. ASME BPE gives slope designations for this, from 0.5% to 2% depending on the service, and the design note says "all lines to slope as per specification". Then the model shows every line dead level, because level is how the pipe tool draws it by default.
Clash detection runs on that model. Ductwork, cable trays and sprinkler mains get routed around level pipes. By the time the fitter arrives, the only space left is the space the model promised, and a 1% fall over a 30 m run needs 300 mm of height that nobody reserved. The fitter installs it level, or with a belly where it meets a duct. The general note does not win against a ceiling void.
What has to be in the model, not in a note:
- Every clean-utility line drawn at its real slope and direction of fall.
- Low-point drains and high-point vents as modelled components, with access.
- The slope included in the clash check, so services are routed around the pipe as it will be built.
This is one reason we coordinate clean utilities in BIM from basic design and not as a detail-stage afterthought. It costs modeling hours early and saves a drain-down failure during OQ.