What 21 CFR 11.10(e) asks of an EMS audit trail

  • Life Sciences
  • 1 min read

21 CFR 11.10(e) asks for "secure, computer-generated, time-stamped audit trails". A logbook beside the EMS is none of those.

Start with who writes the entry. The system has to record each change as it happens, with the user, the old value and the new one. A handwritten note about an alarm limit helps an investigation, but the inspector will ask for the software's record.

Security means nobody can edit or delete an entry, the administrator account included. Plants get caught by housekeeping here: an archive job or database purge that drops old trail entries is a data integrity problem, however tidy the result looks.

A time stamp only helps if the clocks agree. Synchronise the EMS server, the particle counters and any data loggers to one time source and record the time zone, or the order of events cannot be rebuilt after an excursion.

The paragraph also asks that changes do not obscure earlier entries, and that the trail is kept as long as the records it covers.

For an environmental monitoring system this is URS material. Setpoint and alarm-limit changes, acknowledgements with a reason, user and role changes and data edits all go in the trail, and a named role reviews it on a defined frequency. Many plants keep GMP monitoring on a separate EMS because a BMS built for facility control often lacks these functions.

We design SCADA and monitoring systems to Part 11 and Annex 11, audit trail requirements included in the URS.

Industries

Related

More on this subject

ALCOA+ on the EMS is a design requirement

Environmental monitoring and BMS data that support GMP decisions must meet ALCOA+. In practice that means individual logins, time-synchronized controllers, an audit trail users cannot disable, alarms acknowledged with name and comment, and tested backups, with GMP-critical parameters separated early onto a validated system.

Read

GAMP 5 Second Edition puts critical thinking first

GAMP 5 Second Edition (2022) scales validation effort to risk to patient safety, product quality and data integrity, and adds agile and cloud guidance. On a GMP BMS, test alarms, audit trail and data transfer deeply. A quick check: count low-risk functions that still carry full test scripts.

InsightRead

Infrastructure qualification under a GMP SCADA

Servers, network, virtualisation, backup and time sync under a GMP system are qualified as a controlled platform; the application on top is validated for its intended use. With the platform qualified, a routine OS patch needs an impact assessment and a targeted check, not a new OQ of the SCADA.

InsightRead