Annex 11 supplier assessment belongs in the validation plan

  • Life Sciences
  • 1 min read

Before a SCADA or EMS goes into a GMP plant, Annex 11 expects a written view of the supplier's competence and reliability.

Clause 3.2 is two sentences long: supplier competence and reliability are key factors, and the need for an audit should be based on a risk assessment. A desk assessment can be enough for a low-risk tool; a system holding monitoring data used for batch release may justify a visit. Either way, the reasoning goes on paper.

For a SCADA, BMS or environmental monitoring system, the assessment usually covers:

  1. The supplier's quality system and how they control software versions and releases.
  2. Their development and test records, for the product and for your configuration.
  3. How they report and fix defects after go-live, and how quickly.
  4. Who can reach the system remotely, and how that access is recorded.

GAMP 5 (second edition, 2022) supports using good supplier documentation to reduce the testing the regulated company repeats. The reduction has a floor. The user still owns the URS, the risk assessment and the configuration-specific tests. Alarm limits, user roles and audit trail settings are configuration, and only the site's own tests show they are set right.

We write the URS and validation strategy in parallel with design. That is also the cheapest moment for the supplier assessment, while the purchase order is still open.

How we plan validation alongside design

Industries

Related

More on this subject

GAMP 5 Second Edition (2022) scales validation effort to risk to patient safety, product quality and data integrity, and adds agile and cloud guidance. On a GMP BMS, test alarms, audit trail and data transfer deeply. A quick check: count low-risk functions that still carry full test scripts.

InsightRead

GMP on the electrical side

Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.

InsightRead

Servers, network, virtualisation, backup and time sync under a GMP system are qualified as a controlled platform; the application on top is validated for its intended use. With the platform qualified, a routine OS patch needs an impact assessment and a targeted check, not a new OQ of the SCADA.

InsightRead