Mid-inspection, the engineering manager is asked who decides that a room is fit to use after a filter change.

If the answer is "QA", the next question is what QA looked at before deciding, and who produced it.

"Quality is QA's job" is said in most plants. The GMP texts read differently.

The 2013 text of EU GMP Chapter 1 opens by making the quality objective the responsibility of senior management, and says it requires the participation and commitment of staff in many different departments and at all levels. ICH Q10 gives senior management the ultimate responsibility for an effective quality system.

In Chapter 2, the head of Production generally has the responsibility to ensure the qualification and maintenance of his department, premises and equipment. The chapter also says the manufacturer should provide training for the technical and maintenance personnel whose duties take them into production areas.

Engineering as a department is not mentioned in either chapter. In most plants it does this work on behalf of the heads who are named: it holds the drawings, the calibration records and the requalification dates.

A better answer to the inspector names both: QA releases the room, on evidence that engineering produced and can explain.

Industries

Related

More on this subject

A month-end note from Tony Nguyen, CEO

After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.

InsightRead

Campaign length belongs in the cleaning validation

Batches of one product run back to back leave more baked-on product, packed fines and microbial growth for the final clean. The 2015 text of EU GMP Annex 15 (clause 10.9) says the maximum length of a campaign, in time and/or number of batches, should be the basis for cleaning validation. Set that maximum and validate after it.

InsightRead

Cleaning validation in EU GMP Annex 15, and the hold times

Five points of EU GMP Annex 15 (2015) shape a cleaning validation protocol: all product contact equipment, residue limits based on a toxicological evaluation, dirty and clean hold times, dedicated equipment or other appropriate measures where cleaning is ineffective, and manual cleaning confirmed at a justified frequency. All five are written with 'should'.

InsightRead