Two weeks ago an unsealed ceiling penetration was one line on a punch list. Found during an OQ pressure test, it is a deviation.
That means an investigation, a retest and a record an inspector will read, and it is the real price of starting qualification "in parallel" while the contractor closes punch items.
Commissioning and qualification can use the same instruments and even the same methods. What differs is what the result becomes. A commissioning run is engineering: find the problem, fix it, run again. A qualification test is GMP evidence, executed against an approved protocol, and a failure is documented as one.
So the order matters:
- Commission and balance the system until it performs, and keep those results.
- Close every punch item that could affect a qualification test, and name which ones they are.
- Then execute IQ and OQ, on a system you already expect to pass.
Qualification cannot start from an open punch list, but it can start early: turn over one AHU and its rooms at a time, so finished systems move on while construction carries on elsewhere.
In our EPCM work, construction to qualification is one of four handovers we manage explicitly, with FAT, SAT and commissioning records feeding into IQ.