EN 1886 class L2 allows an AHU casing 0.44 l/s per m² of leakage at −400 Pa. On a witnessed FAT, casing leakage, fan airflow at design static pressure, filter bypass and the control panel are checked against the approved specification, and both engineers sign the sheet that goes into the equipment file.
Cooling coils pay for dehumidification in chiller kWh; desiccant rotors mostly in reactivation heat, often above 100 °C for silica gel rotors. Compare them by listing the heat the site already has and its temperature. Very low dew points need desiccant regardless, and rotor outlet air still needs cooling.
AHU quotations show price, rarely running cost. EN 13053 velocity, fan power and heat recovery classes, declared at design airflow, make offers comparable on energy. Without them the tender is judged on capital cost and the pressure drop of a small casing shows up later in fan energy.
A full-size 592 × 592 mm bag filter is commonly rated at about 3,400 m³/h. A 20,000 m³/h AHU needs six frames; a casing with room for four runs each at 47% over, with higher pressure drop, possibly lower efficiency and fluttering pockets. The frame count belongs in the specification and the FAT.
An extra 100 Pa of filter resistance on a 10,000 m³/h supply costs about 460 W, roughly 4,000 kWh a year. The cheapest change point comes when the latest month's extra energy cost exceeds the average monthly cost since fitting, filter set included, provided it sits below the manufacturer's maximum final pressure drop.