A new HEPA filter can arrive with sealant patches on the media and still meet the standard it was tested to.
Pleated glass-fibre media is fragile, and pinholes turn up at the factory leak test. EN 1822-4:2009, the scan-test part that EN ISO 29463-4 replaced in 2018, said a filter may be repaired if necessary and shall then be retested, and capped the repairs: all of them together, whoever made them, not more than 0.5% of the filter face area, frame excluded, and no single repair longer than 3.0 cm, unless buyer and seller agreed other criteria. Ask which text the supplier's report cites and read its repair clause.
On a media face of 570 × 570 mm, 0.5% is about 16 cm²: a few beads of sealant.
Most purchase orders say nothing about any of this, so the supplier's default applies and nobody on the project chose it. Three lines settle it: whether repaired filters are accepted, to which limit, and that each repair is marked on the scan test report shipped with the filter. Some owners accept no repairs on filters above Grade A zones and pay more for them.
The three lines cost nothing on a filter that arrives clean. They decide who chose the limit on the one that does not.
Topics