After a ceiling change: add the air or justify the ACH

  • News
  • 1 min read

Raise the ceiling of a 6 × 5 m room from 3.0 m to 3.5 m, keep the supply air, and the air change rate falls from 20 to 17.1.

The numbers: at 3.0 m the room holds 90 m³, and 1,800 m³/h gives the 20 air changes the URS asked for. At 3.5 m it holds 105 m³. Keeping 20 ACH needs 2,100 m³/h.

That extra 300 m³/h is about 17% more through the room's terminal HEPA, its branch duct and its share of the coil, fan and reheat. On a tightly selected AHU it can push the unit past its duty point, and where every room in a suite moved together it can mean a different AHU.

Staying at 1,800 m³/h changes less than the ACH figure suggests. In a well-mixed room the steady-state particle count is the generation rate from people and process divided by the supply airflow. Room volume is not in that ratio, so with the same operators, process and supply air the in-operation count stays about where it was. Volume matters for the transient: the time constant is volume over airflow, so recovery after a disturbance takes about 17% longer.

Which way to go depends on what the 20 was protecting. A recovery-time requirement argues for the extra air. An ACH carried over from a guideline is better replaced by the recovery time it was meant to deliver, then tested. Both routes need a change control against the URS.

Which way did your last ceiling change go?

Related

More on this subject

AHU casing deflection: D1 or D2

EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.

InsightRead

Manufacturing & Distribution

Clean the new AHU before its first fan run

A new AHU started during construction loads its coil, drain pan and final filters with site dust that does not vacuum off wet fins. Clean the casing before power-on, seal duct openings, run on temporary pre-filters, fit final filters after the final clean and record it for IQ.

InsightRead

Containment exhaust fans, stacks and intakes

Put containment exhaust fans at the end of the run so ducts inside the building stay negative. Run duty and standby with isolation dampers and alarmed changeover, discharge vertically with height and velocity from a standard or a dispersion study, and keep the plume away from fresh-air intakes.

InsightRead