The EN 1822 class on a HEPA filter holds at the airflow it was tested at. Push more air through the same filter and three things move.
- Pressure drop rises. Flow through fibrous media is laminar, so resistance is roughly proportional to media velocity. Around 20% more air means roughly 20% more initial pressure drop, and the fan has to find it until the end of filter life.
- Diffusion capture falls. The smallest particles are caught because Brownian motion makes them wander into fibres. At higher velocity each one spends less time in the media and has fewer chances to hit something.
- The most penetrating particle size shifts smaller, and penetration at that size rises. A filter classed H14 at its nominal flow may not reach H14 efficiency at 120% of it.
None of this shows on the label. It shows up as a fan running near its limit, or a leak test result that is hard to explain.
The usual cause is ordinary. An FFU or terminal housing is selected for the airflow schedule of an earlier design revision, then asked for more air after the room layout changes. The fix is more filter area, or a written check that the rated flow still covers the new duty.
We select HEPA filters from the project's own airflow schedule and keep the rated flow in the equipment file, so a later change has something to be checked against.