Most HEPA damage happens between the truck and the ceiling, and it stays hidden until the installed leak test.
A filter leaves the factory leak-tested and certified. Then it rides in a container, is unloaded by forklift, waits in a site store through weeks of construction dust and humidity, and is carried up a scaffold. The media is a pleated paper of glass fibre. A thumb through the carton wall is enough.
The checks, from the delivery note to the ceiling:
- Cartons arrive dry, uncrushed and standing the way the arrows show. Photograph any damage before signing the delivery note.
- The label on each filter gives class, serial number and rated airflow, and all three match the filter schedule and that filter's own test report.
- Storage is indoors, dry, off the floor, in the original carton, stacked no higher than the carton marking allows.
- The carton is opened only at a clean work area next to the ceiling position, on the day of fitting.
- Before it goes up, media and gasket are inspected on both faces under a strong light. The filter is carried by its frame.
Under EN 1822, filters of class H13 and above are leak-tested one by one at the factory, which is why each has its own report and serial number. That test says nothing about what happened afterwards.
A dent found on the floor costs one filter. The same dent found by the aerosol scan costs the filter, a ceiling opening and a repeat test.