On a new desiccant dehumidifier everyone asks for the outlet dew point first. It is the reading to take last.
A rotor reaches its selected performance only when the airflows, the heat and the seals around it are right, so commissioning goes through those first.
- Check the rotor. It turns in the direction of the arrow at the speed on the data sheet. The drive belt is tensioned and the face seals touch all the way round.
- Set the process and reactivation airflows, and measure both. A reactivation flow that is short leaves water in the wheel, and no setting downstream makes up for it.
- Test the interlocks before the heater is left running: no heat without proven reactivation airflow, the over-temperature cut-out, the rotor rotation alarm, and the fan run-on that cools the heater after a stop.
- Set the reactivation temperature at the rotor inlet to the selection value.
- Now measure dew point at the process inlet and outlet, and compare the moisture removed with the selection at that inlet condition. An outlet figure alone says little: a unit selected for wet-season air looks excellent on a dry morning.
At low dew points the sensor and its sample line take hours to dry down. A reading taken ten minutes after start mostly reports the tubing.
Humiley supplies desiccant dehumidification down to −60 °C dew point. Where the manufacturer's commissioning sheet differs from this order, follow the sheet.