At 21 °C, holding 45% RH needs supply air at a dew point of about 8.6 °C. At 55% RH the figure is about 11.6 °C.
That 3 K is paid at the cooling coil every hour the plant runs. Reaching 8.6 °C takes colder chilled water or a deeper coil, and the air it produces is cold enough that much of it gets reheated before it can be supplied. At 11.6 °C the same plant runs on warmer water, the chiller works less hard, and the reheat shrinks.
Many cleanroom URS documents carry 45 ± 5% RH for every room, copied from the last project. Some products need a tight, low band: hygroscopic powders, effervescent blends, some capsule work. Plenty of rooms, corridors and airlocks don't, yet they end up on the same AHU as the one room that does.
Before the band goes into the URS:
- Ask what the product data requires, and for which rooms.
- Put rooms with tight bands on their own AHU, or dry their fresh air separately, so one room doesn't set the coil for the rest.
- Write each band with its reason, so it can be challenged at DQ rather than inherited.
This is one of the places the 30% HVAC energy reduction we target in energy modeling comes from, with no condition a product needs loosened.
What RH band does your Grade C corridor carry, and who chose it?