On a wet-season afternoon in southern Viet Nam, an air-side economiser has nothing to offer a cleanroom.
The outdoor air holds more than twice the energy per kilogram of the air leaving the room.
Take a worked example. Outdoor air at 29 °C with a 26 °C dew point carries about 84 kJ/kg. Return air from a room at 20 °C / 45% RH carries about 37 kJ/kg. Air-side free cooling only saves energy when outdoor enthalpy is below return enthalpy. Here it is more than double, and in this climate the gap barely closes at night, because the dew point hardly moves.
So energy models copied from temperate projects, with an economiser mode and a count of free-cooling hours, promise savings that the weather will not deliver. In a GMP plant the fresh air is also set by pressurisation and occupancy, so there is little appetite for raising it anyway.
In the tropics the savings are somewhere else. Most of the fresh-air load is latent, so how and where you dehumidify matters more than anything else. Reheat after overcooling is often the largest avoidable cost. Fan power runs every hour of the year. And chilled water that is warmer where coils only need to cool, not dry, lowers the chiller lift.
Our energy modeling targets a 30% reduction in HVAC energy, and in this climate almost none of it comes from economiser hours.