Write both occupancy states into the URS

  • Life Sciences
  • 1 min read

"Grade B (ISO 7)" in a URS is half a requirement, and the missing half is the stricter one.

EU GMP Annex 1 (2022) sets every grade in two occupancy states, each tied to an ISO 14644-1 class for particles ≥ 0.5 µm:

  • Grade A: ISO 5 at rest and in operation
  • Grade B: ISO 5 at rest, ISO 7 in operation
  • Grade C: ISO 7 at rest, ISO 8 in operation
  • Grade D: ISO 8 at rest; the in-operation limit is set by the site

At rest, Grade B allows 3,520 particles ≥ 0.5 µm per m³. In operation it allows 352,000. A URS that quotes only "ISO 7" invites a design sized for the looser number, and the room still has to prove ISO 5 at rest when it is classified.

The rest of the line matters too. "In operation" in Annex 1 means the process running with the maximum number of personnel present. If the URS doesn't say how many that is, the in-operation classification is tested with whoever turned up that day.

A Grade B URS line that can be designed and tested states:

  1. The grade, with its ISO class at rest and in operation.
  2. The maximum number of people in the room.
  3. The clean-up period back to at-rest limits, fixed during qualification.

Then design, DQ and classification argue from the same numbers.

Industries

Related

More on this subject

Annex 1 has applied since 25 August 2023

The revised EU GMP Annex 1 has applied since 25 August 2023, with point 8.123 following in 2024. A site still planning its gap assessment is years behind. Most findings land in the CCS, for example a pressure alarm delay set at commissioning that nobody can justify.

InsightRead

Annex 1's scope reaches non-sterile plants

The scope of EU GMP Annex 1 (2022) says some of its principles, including the contamination control strategy, may be used for certain non-sterile products such as liquids, creams and ointments. A semi-solids plant that writes a CCS tying room grades, flows, water and monitoring to product risk has an answer for the inspector.

InsightRead

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.

InsightRead