If the first validation document on your project is an IQ protocol, validation started late.
The V-model is drawn as a sequence, URS → DQ → IQ → OQ → PQ, and the picture leads people to think the left side is paperwork and the right side is the real work. The picture undersells the left side: every test on the right is only as good as the requirement on the left that it traces back to.
- URS: written before concept design, by the user, in measurable terms. "Grade B, ISO 5 at rest" can be tested. "Suitable cleanroom" cannot.
- DQ: documented proof that the design meets the URS. It happens at design stage, against drawings and calculations, while changes are still cheap.
- IQ: the installation matches the approved design. Its protocol should be drafted from the same documents the contractor builds from.
- OQ: systems perform across their operating ranges: airflow, pressure differentials, recovery, alarms.
- PQ: consistent performance under real operating conditions, over time.
A traceability matrix links every URS line to its design reference and its test. Started on day one, it shows gaps while they are still drawing changes rather than site changes.
Humiley writes the URS, validation strategy and qualification roadmap in parallel with the design.
Who writes the URS on your projects: the user, the designer or the contractor?
Industries




