A BMS setpoint edit is a GMP change

  • Life Sciences
  • 1 min read

Nobody touched a duct.

Someone changed a room pressure setpoint from 15 Pa to 12 Pa in the BMS, and the room is no longer in the state it was qualified in.

On a running site it usually starts with a nuisance alarm. A door alarm keeps tripping, someone nudges the setpoint, the alarm stops. Or the RH setpoint moves a couple of points to save reheat in the dry season. The screen accepts the value, the audit trail records a username, and the change control system never hears about it.

EU GMP Annex 15, section 11, asks for changes that may affect qualified status to go through change control. Annex 11 says changes to a computerized system, configuration included, are made in a controlled manner under a defined procedure. A setpoint is configuration. It is also a qualified parameter: the OQ tested the cascade at the original values.

So a setpoint edit takes the same route as a duct modification. Raise the change, state the reason, assess the impact on the cascade and on the Contamination Control Strategy, decide what has to be retested, then make the edit.

Two controls help in practice. Lock qualified setpoints behind a role that the maintenance login does not hold. And read the BMS audit trail for setpoint changes at every periodic review, not only after a deviation.

How are qualified setpoints protected in your BMS today?

Industries

Related

More on this subject

GMP on the electrical side

Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.

InsightRead

Metadata: what a stored value needs to mean anything

A stored value of 22.4 means nothing without its sensor tag, unit, time stamp, status flag, author and audit trail. The MHRA's 2018 data integrity guidance defines metadata as data that describe the attributes of other data and provide context and meaning. Test that backups, exports and migrations carry them.

InsightRead

Part 11 starts with the predicate rule

Part 11 applies to electronic records that a predicate rule such as 21 CFR 211 requires. For a BMS or EMS, name the rule behind each point: GMP-critical monitoring usually belongs in a validated EMS. For EU export, Annex 11 has no predicate-rule test, so the BMS still needs a risk assessment.

InsightRead