Oral liquids: the contamination points sit low

  • Life Sciences
  • 1 min read

A liquids suite gets washed down far more often than a tablet room, and every litre of that water has to leave the room somewhere.

That is the difference from a dry room. The contamination points sit low: floor drains, the falls that lead to them, the joint between floor and wall, the point-of-use valves on purified water. A drain that still holds water after cleaning is a place for biofilm, a metre from the product.

What we look at in a liquids suite design:

  1. Floor falls that actually reach the drain, with no ponding after a wash.
  2. Drains with traps and covers that can be cleaned and disinfected, and no drain at all in rooms that do not need one.
  3. Coved junctions between floor and wall, so no corner holds water.
  4. Purified water outlets that drain fully and can be sanitized, with a sampling point that represents what the product sees.
  5. Extract and airflow sized for the moisture a wash-down releases, so walls dry before the next shift.

None of these fixes itself after handover. A floor fall is set on the day the screed is poured, and correcting it later means breaking out the floor.

Our clean utilities scope covers PW, WFI and Pure Steam with the process piping, and outlet and drain positions are settled with the room layout rather than after it.

See how we work

Industries

Related

More on this subject

Scale-up is more than a bigger batch size

Five times the batch at the same set-points gives different granules, because some parameters depend on scale. WHO's technology transfer guideline says batch sizes should be compared and the impact assessed where they differ. Compare the equipment, check dust, exhaust and water at the new scale, and settle set-points with trial batches.

InsightRead