Plenty of change records close on the day the new equipment is installed. ICH Q10 asks for one more step.
Its change management section expects an evaluation after implementation, to confirm the change achieved what it was meant to and did no harm to product quality. Installing the part is only the start of that.
Take a common one. A room has had humidity excursions every wet season, so the change replaces the dehumidifier controller. The controller goes in on a Friday, the SAT passes, and the change is closed the same afternoon. Nobody writes down what "fixed" would look like, so when the wet season arrives and the excursions come back at a lower rate, there is no agreed way to say whether the change worked.
The fix is to write the effectiveness check when the change is approved:
what data will show the objective was met (excursion count, trend of the room RH);
over what period, long enough to include the conditions that caused the problem;
and what result closes the change, or reopens it.
Written after the fact, the check tends to become "no complaints received".
Our maintenance service runs condition monitoring and trending on the systems we look after, and that trend data is what an effectiveness check on an HVAC change usually needs.
How long does your site wait before judging an HVAC change effective?