Two engineering proposals for the same GMP suite can carry similar totals and very different scopes.
The difference usually sits in the deliverable list. Often one proposal names every document and the other says "HVAC design", leaving the rest to be found after award, as a variation.
Before comparing totals, put the deliverable lists side by side and check that each one names:
- Room Data Sheets for every room: grade, temperature and RH ranges, pressure to each neighbour.
- The pressure cascade drawing and the airflow and pressure balance behind it.
- The URS, the validation strategy and the qualification protocols. "By others" on any of them means someone still has to write it, and pay for it.
- For equipment, the FAT and the equipment file (material certificates, FAT report, O&M manuals, spares), so IQ does not start from a missing record.
- For maintenance, an asset register with a criticality assessment behind the response times.
A line present in one list and missing from the other is worth a question to both bidders before anyone looks at the price.
On our projects the URS, validation strategy and qualification roadmap are written in parallel with the design, so they sit on the deliverable list from the first issue.