Nearly every watt of electrical power used inside a cleanroom ends up as heat in the room air.
Only what a water circuit or an exhaust duct carries away escapes. That is the first law, and it is why a load template built on people, lighting and a general equipment allowance keeps producing rooms that run warm once production starts. The heat the template missed was in the room all along. The ones we see missed most:
- Autoclave and steriliser bodies. The chamber is insulated. The door face, the loading end and the pipework often are not, and they sit in the clean room while the machine room gets the rest.
- Depyrogenation tunnels. Skin losses along the whole length, plus the hot-zone exhaust if it is not ducted away.
- Hot water and steam loops in the ceiling void above the room. The void warms, and the ceiling passes that heat down.
- Electrical panels and drives installed inside the room because the cable run was shorter.
- Fan-filter units. Every FFU motor sits in the supply air it is pushing into the room.
None of these is hard to calculate. They are just not on the template, so nobody asks. The process team knows the connected loads and surface temperatures. The HVAC team has to go and get them.
We size air handling from the project's own load calculation, so the process equipment list is one of the first documents we ask for.