10,000 m³/h through a 700 × 500 mm duct moves at about 8 m/s. Squeeze it to 600 × 400 mm to clear a cable tray and it runs at about 12.
That change looks like coordination. It is a fan decision. Velocity pressure is about 0.6 v² in pascals: roughly 38 Pa at 8 m/s and 80 Pa at 11.6 m/s, the exact speed in that duct. Every elbow, tee and take-off loses a multiple of velocity pressure, so each fitting on that run now costs about twice what it did. Friction per metre more than doubles too, because the duct is smaller as well as faster. The fan pays for it every hour the plant runs, and a cleanroom AHU runs all of them.
Noise moves the same way. Fittings and dampers regenerate noise that climbs steeply with velocity, and GMP supply ducts rarely carry internal acoustic lining to soak it up.
Mains and branches deserve different limits. The main runs through the plant room and riser, where higher velocity buys space and the noise has distance to fade. Branches end at terminal HEPA boxes just above the room, where regenerated noise is heard, and a balancing damper working at high velocity is hard to set finely.
Write the velocity limit for each duct role into the design basis before BIM coordination starts, and list every run that exceeds it with the reason.
What limits does your design guide set for mains and for branches?
Industries




