Keep the cleanroom ceiling void below the room

  • News
  • 1 min read

The air above a cleanroom ceiling has never been through a HEPA filter.

It sits among ducts, cable trays and the backs of light fittings, separated from the room by panel joints and dozens of penetrations, each sealed as well as the installer managed that day. Whether that air stays up there depends on one thing: the pressure of the void relative to the room.

With the room higher, every leak runs from room to void and carries filtered air out. That costs a little supply airflow. With the void higher, the same leaks run the other way and bring unfiltered air down past light frames and HEPA housing collars.

Voids end up positive more often than drawings suggest. Leaking supply duct joints pressurise them. So does a void that opens to a plant room, or to an outside wall facing the wind. And one void spanning rooms at 30, 15 and 0 Pa has to sit at or below the lowest of them, or it feeds the 0 Pa room from above.

The fixes are ordinary: seal and leak-test the duct joints, vent the void to an unclassified space at a known pressure, and put a room-to-void pressure check into the commissioning scope so the direction is measured rather than assumed. We coordinate the void, its vents and its penetrations in the BIM model before the ceiling panels are cut.

How does your team check the direction of flow across a walkable ceiling?

Related

More on this subject

The HEPA housing joint the filter scan misses

The installed HEPA scan covers media, frame and the filter-to-housing seal, but not the flange between housing and ceiling. Where the ceiling void runs at higher pressure than the room, unfiltered air enters there. Seal it with an evenly compressed gasket and sealant bead, then probe the flange and file the result.

InsightRead

Central Vacuum Cleaning

In GMP audits, scrutiny often lands on Cleaning Procedures. Using portable vacuum cleaners in cleanrooms is a red flag. Why? Because the exhaust turbulence from a portable unit disrupts laminar airflow and can aerosolize settled dust,…

InsightRead